peterborough 07/08/2014 at 12:36 #63602
CABOOSEMAN
Avatar
35 posts
Whilst travelling north on Tuesday I saw what looked like new sidings being laid north of station,but before EASTFIELD box any idea what these are for and what work is being done between Peterborough and Spalding is it upgrading and resignalling. Many Thanks Cabooseman [Martin]
Log in to reply
peterborough 07/08/2014 at 13:55 #63605
dwelham313
Avatar
139 posts
The new sidings to the north of the station are part of the Thameslink programme for stabling of class 700s. A wash plant is also to be built I believe.
Log in to reply
The following user said thank you: CABOOSEMAN
peterborough 07/08/2014 at 15:00 #63610
bandiez
Avatar
62 posts
The line between Peterborough and Spalding is being upgraded (GNGE project). New signalling and upgrading level crossings controlled by Lincoln SCC. It is for sending North/South bound freight via lincoln to increase capacity on the ECML. Also believe it will increase line speeds on the line to 75MPH. http://www.networkrail.co.uk/improvements/Great-Northern-Great-Eastern/ has the details.
Last edited: 07/08/2014 at 15:02 by bandiez
Log in to reply
The following user said thank you: CABOOSEMAN
peterborough 08/08/2014 at 09:41 #63633
CABOOSEMAN
Avatar
35 posts
Many thanks for the information Regards Cabooseman
Log in to reply