Wembley August 2012 Olympics TT Released 20/09/2014 at 13:09 #64654 | |
Underwood
![]() 748 posts |
Hello all, The next TT in the Olympics set is now released for Wembley Mainline. The timetable covers 24 hours on a general weekday during early August, and features the late night extra services by London Midland, Virgin Trains and London Overground, and also the Olympic relief sets from Wembley EFOC. I've tested the early morning part as I had to swap around some 378's, but it should work now. I haven't tested the whole TT as I am tying up some ends on my Marlyebone weekend diversion TT. The majority of it should work, however if you do find any faults please do post them here so that I can edit them all for a V1.1 release if needed. Once I've sorted Marylebone, I just need to add the St Albans shuttle into my Watford 2012 Olympics TT, then I'll release that which will chain to Wembley. Enjoy! James. Log in to reply The following users said thank you: tjfrancis, Sidestick Priority, John, Banners88 |
Wembley August 2012 Olympics TT Released 21/09/2014 at 08:09 #64668 | |
John
![]() 884 posts |
James, 5Z23 seeds but it's schedule is for 24 hours later. 4M90's schedule has the best part of an hours slack between Willesden West London Jn and Willesden No.7. I'm guessing that it recesses at Acton Lane, but the schedule does not reflect this. Last edited: 21/09/2014 at 10:07 by John Log in to reply |
Wembley August 2012 Olympics TT Released 21/09/2014 at 11:39 #64674 | |
Underwood
![]() 748 posts |
Hello John, Thanks for the post: 5Z23 - Whoops, thought I fixed that :blush: I'll change that for the update 4M90 - Yes timings are right but unsure of it's recess, as there is no timing at all for Acton Lane Reception, how it reads in the WTT is: Willesden West London Jn 01/51h Willesden No7 02/52h DR No timings for Acton Lane or Willesden Euroterminal Log in to reply |