Bristol PSB to TVSC - Stage 1..... 08/02/2016 at 20:38 #80480
DaveHarries
Avatar
1272 posts
Evening all,

A quick heads-up regarding the last weekend of May 2016.

It seems that a substantial amount of work is to take place around the Bristol PSB area between Saturday 28th and Monday 30th May inclusive and I have had it suggested on another forum that this is likely to be resignalling of Bristol PSB (Panel D) to TVSC Didcot.

GWR have put a map on a leaflet that is available on their website (the leaflet relates to other works) but I have attached the map to this post. For the benefit, however, of anyone who has trouble seeing it a summary of the situation over the weekend of 28th - 30th May would be this:

Bus Replacement Services:
- Severn Beach to Bristol Temple Meads
- Bristol Parkway to Newport
- Bristol Parkway to Swindon
- Bristol Parkway to Gloucester
- Bristol Temple Meads to Filton Abbey Wood & Bristol Parkway
- Bristol Temple Meads to Severn Tunnel Junction / Newport

So the area closed also includes the whole of Filton Bank. Going by the map attached to this post it seems that Cross Country services will make a detour between Bristol Temple Meads and Gloucester (Standish Junction) via. Bath Spa, Chippenham, Swindon and Kemble. I wouldn't mind that trip for a bit of variety.

If this is for resignalling I wonder if this will be commissioning of part of the area or simply preparation work (ie. installation of signals and equipment) but the number of routes closed suggests something substantial.

HTIOI,
Dave

Post has attachments. Log in to view them.