Watford North Junction

You are here: Home > Forum > Simulations > Released > Watford Junction > Watford North Junction

Page 1 of 1

Watford North Junction 24/01/2021 at 15:54 #136736
9pN1SEAp
Avatar
1100 posts
Online
Hi,

In the manual it states
Quote:
Given the linespeed of the single lead junction immediately to the south of Watford Junction, it would be better to use the faster Watford North Junction instead if crossing from fast to slow or vice versa.
This is of course only true for timetables set prior to it, and the single ladder on South Junction, being plain-lined (2016?) :)

Thanks
Jamie

Jamie S (JAMS)
Last edited: 24/01/2021 at 16:21 by 9pN1SEAp
Reason: None given

Log in to reply
The following user said thank you: Trainfan344
Watford North Junction 24/01/2021 at 16:08 #136737
y10g9
Avatar
895 posts
But this was true at the time that the manual was written
Log in to reply
The following user said thank you: pedroathome
Watford North Junction 24/01/2021 at 16:25 #136742
Steamer
Avatar
3913 posts
y10g9 in post 136737 said:
But this was true at the time that the manual was written
And Watford Jn PSB (which is what the simulation represents) closed in 2014.

"Don't stress/ relax/ let life roll off your backs./ Except for death and paying taxes/ everything in life.../ is only for now." (Avenue Q)
Log in to reply
The following user said thank you: y10g9
Watford North Junction 24/01/2021 at 18:13 #136744
GeoffM
Avatar
6274 posts
^^^What they said. But I did fix an errant apostrophe in the manual just now.
SimSig Boss
Log in to reply
Watford North Junction 24/01/2021 at 18:44 #136750
madaboutrains
Avatar
307 posts
Just out of curiousity can anyone please confirm the current status on the junction? Last time I went to Wembley box the junction was out of use but I dont believe it has been put back into commission since?

Open Train Times for what ever reason is showing plain line on the North side of the station. https://www.opentraintimes.com/maps/signalling/lec2#T_WATFDJ

Thanks in advance

RIP Feltham Panel 1
Last edited: 24/01/2021 at 18:44 by madaboutrains
Reason: None given

Log in to reply
Watford North Junction 24/01/2021 at 18:53 #136752
headshot119
Avatar
4869 posts
madaboutrains in post 136750 said:
Just out of curiousity can anyone please confirm the current status on the junction? Last time I went to Wembley box the junction was out of use but I dont believe it has been put back into commission since?

Open Train Times for what ever reason is showing plain line on the North side of the station. https://www.opentraintimes.com/maps/signalling/lec2#T_WATFDJ

Thanks in advance
LNW(S) Sectional Appendix December 2020 - Table A - MD101 - 010 (Last updated 19/09/2015) notes Watford North Junction as out of use until further notice.

I can't see any changes to that in more recent PONs either.

"Passengers for New Lane, should be seated in the rear coach of the train " - Opinions are my own and not those of my employer
Last edited: 24/01/2021 at 18:53 by headshot119
Reason: None given

Log in to reply
Watford North Junction 25/01/2021 at 23:39 #136776
Guts
Avatar
584 posts
Still out. They're talking about installing it this year but for ulterior motives
Log in to reply
The following user said thank you: madaboutrains
Watford North Junction 28/01/2021 at 14:35 #136822
8stewartt
Avatar
33 posts
When the resignalling was done, the interlocking provided everything for the junction, and I believe all the signals associated with it are in work, just no pointwork. I also remember (I think) the possession where it was to be installed was cancelled as, the chiltern line was stepped up to cater for additional traffic, but there was a landslide closing a tunnel on the chiltern route, so this got cancelled to reopen the WCML. Would be good to see it back in, theres be times in recent years where it would have been useful to have it!
Log in to reply