Upcoming Games

No games to display

Full list
Add a game

Upcoming Events

No events to display

No Platform 2 at Portsmouth Harbour

You are here: Home > Forum > General > General questions, comments, and issues > No Platform 2 at Portsmouth Harbour

Page 1 of 1

No Platform 2 at Portsmouth Harbour 05/07/2015 at 20:42 #73932
Myrm
Avatar
36 posts
Hi

I have been playing this sim for a few months now and still enjoying, but it's taken me all this time to notice that there is no platform 2 in the Portsmouth Harbour sim.

Log in to reply
No Platform 2 at Portsmouth Harbour 05/07/2015 at 21:10 #73934
kaiwhara
Avatar
584 posts
" said:
Hi

I have been playing this sim for a few months now and still enjoying, but it's taken me all this time to notice that there is no platform 2 in the Portsmouth Harbour sim. :laugh:
Someone local will probably add more detail or correct me, but Platform 2 was removed some years ago. Something to do with the structural integrity of the Pier I believe?

Sorry guys, I am in the business of making people wait!
Log in to reply
The following user said thank you: Myrm
No Platform 2 at Portsmouth Harbour 05/07/2015 at 21:14 #73936
sloppyjag
Avatar
480 posts
It's still there but not used as there is no track in the trackbed. I seem to recall there was some remedial work done in the 90's to stop the station collapsing into the Solent and the track in P2 was never replaced.

Edit: Kiawhara typed faster.

Planotransitophobic!
Log in to reply
The following user said thank you: Myrm
No Platform 2 at Portsmouth Harbour 05/07/2015 at 21:14 #73937
Myrm
Avatar
36 posts
KK, thank you.
Log in to reply
No Platform 2 at Portsmouth Harbour 05/07/2015 at 22:10 #73940
Cedric
Avatar
42 posts
Substantial structural remedial work was done on the pier supporting Portsmouth Harbour station in the 1990s. As a cost-cutting measure a decision was taken not to reinstate Platform 2, and although the space where the former track was still exists my understanding is that the present structure is not designed to take the weight of a reinstated platform.

The effect of removing platform 2 is that capacity at Portsmouth Harbour has been somewhat restricted in a period that has seen substantial passenger growth, with Portsmouth & Southsea being used to terminate trains that might otherwise have gone through. Decisions about Portsmouth Harbour were taken in the midst of privatisation when, if I recall, the focus within the industry was much more about organisational structure than about train performance and system capacity. If the decision was being taken now I suspect that Platform 2 would have been rebuilt.

Hope that helps
Cedric

Log in to reply
The following user said thank you: Myrm