Upcoming Games

No games to display

Full list
Add a game

Upcoming Events

No events to display

Manchester North - 2007 Timetable

You are here: Home > Forum > Simulations > Timetables > Manchester North > Manchester North - 2007 Timetable

Page 1 of 1

Manchester North - 2007 Timetable 02/01/2018 at 17:00 #104734
whatlep
Avatar
376 posts
This thread is to log any bugs/ issues found with the TT released on 01/01/2018. Despite several days' testing, as soon as the timetable was released, I immediately found three (sighs heavily)....

1) 6J46FX requires a rule change to prevent it running on Fridays as well
2) ECS 5F15 shows at Newton Heath (Down Rochdale) in error: it ran Saturdays Only
3) Peakstone departures need their departure times to be fixed ("wait for departure time"so they can not leave too early.

All three will be included in V1.1 to be released next weekend. Any further issues identified will also be included in that update.

Hope you enjoy the timetable. Thanks for your patience if you trip over any of the three bugs listed.

Log in to reply
The following users said thank you: HST125Scorton, woodruff
Manchester North - 2007 Timetable 03/01/2018 at 12:01 #104760
whatlep
Avatar
376 posts
More issues/ bugs identified. I will bring forward V1.1 to tomorrow, Jan 4th to minimise inconvenience to users.

- 5M26 runs to far end of turnback siding to ensure space for second working
- approx 40 instances of passing time box not ticked fixed at Deal St, Thorpes Bridge & Miles Platting
- 4E78MO appears twice
- 5J49-2356 should not run (another SO train)

Last edited: 03/01/2018 at 18:42 by whatlep
Reason: None given

Log in to reply
Manchester North - 2007 Timetable 04/01/2018 at 13:19 #104804
whatlep
Avatar
376 posts
Version 1.1 now available, addressing all errors found thus far.
Log in to reply
The following user said thank you: woodruff